 * ''Please do not edit''
 * Freezes normally happen at the start of the given date, UTC time.  So last minute changes need to happen the day before.
 * Some background information and Q&A about the Ubuntu release process can be found on TimeBasedReleases

'''[http://people.ubuntu.com/~scott/FeistyReleaseSchedule.ics Schedule as iCal]'''

||<rowbgcolor="#cccccc"> '''Week''' || '''Date''' || '''Task''' || '''Status''' || '''Notes''' ||
||<-5 #eeeeee> November 2006 ||
|| 1 || November 2nd ||  ||<#CCFFCC> || <!> Toolchain Uploaded ||
|| 2 || November 9th ||  ||<#CCFFCC> || {*} Development Summit ||
|| 3 || November 16th ||  ||<#CCFFCC> || {*} Canonical AllHands ||
|| 4 || November 23rd ||  ||<#CCFFCC> ||  ||
|| 5 || November 30th ||  ||<#CCFFCC> || '''[http://cdimage.ubuntu.com/releases/feisty/herd-1/ Herd CD 1]''', Specifications must be finalized ||
||<-5 #eeeeee> December 2006 ||
|| 6 || December 7th ||  ||<#CCFFCC> ||  ||
|| 7 || December 14th ||  ||<#CCFFCC> ||  ||
|| 8 || December 21st ||  ||<#CCFFCC> /!\ '''DebianImportFreeze''' || <!> Remaining upstream merges completed, Rebuild Test ||
|| 9 || December 28th ||  ||<#FFFFCC> ||  ||
||<-5 #eeeeee> January 2007 ||
|| 10 || January 4th ||  ||<#FFFFCC> ||  ||
|| 11 || January 11th ||  ||<#FFFFCC> || '''Herd CD 2''' ||
|| 12 || January 18th ||  ||<#FFEBBB> ||  ||
|| 13 || January 25th ||  ||<#FFEBBB> || Developer sprint (location TBD) ||
||<-5 #eeeeee> February 2007 ||
|| 14 || February 1st ||  ||<#FFEBBB> || '''Herd CD 3''' ||
|| 15 || February 8th ||  ||<#FFEBBB> /!\ '''FeatureFreeze''', /!\ '''UpstreamVersionFreeze''' || <!> Rebuild Test, Upgrade Testing begins ||
|| 16 || February 15th ||  ||<#FFCCCC> || '''Herd CD 4''' ||
|| 17 || February 22nd ||  ||<#FFCCCC> ||  ||
||<-5 #eeeeee> March 2007 ||
|| 18 || March 1st ||  ||<#FFCCCC> || '''Herd CD 5''' ||
|| 19 || March 8th ||  ||<#FFCCCC> /!\ '''StringFreeze''' ||  ||
|| 20 || March 15th ||  ||<#FFCCCC> /!\ '''BetaFreeze''' || <!> Rebuild Test ||
|| 21 || March 22nd ||  ||<#E47A7A> /!\ '''BetaRelease''' || ||
|| 22 || March 29th ||  ||<#E47A7A> ||  ||
||<-5 #eeeeee> April 2007 ||
|| 23 || April 5th ||  ||<#E47A7A> /!\ '''NonLanguagePackTranslationDeadline''', /!\ '''KernelFreeze''' || <!> Rebuild Test '''Herd CD 6'''||
|| 24 || April 12th || ||<#E47A7A> /!\ '''ReleaseCandidate''', /!\ '''LanguagePackTranslationDeadline''' ||  ||
|| 25 || April 19th ||  ||<#E47A7A> /!\ '''FinalRelease''' ||  ||
|| 26 || April 26th || || || ||
||<-5 #eeeeee> May 2007 ||
|| 27 || May 3rd || || || ||
|| 28 || May 10th || || || ||
|| 29 || May 17th || || || ||
|| 30 || May 24th || || || ||
|| 31 || May 31st || || || ||